Extraction of breaklines

The contractor has to extract all breaklines needed for machine control from the model 'Corridor for roads and paths'.

Be aware that the model 'Corridor for roads and paths' contains all breaklines and components used to construct the road in the design phase.

At the cross-sections below, it is described which breaklines for final road level and formation level the contractor can use for machine control.

The layers between the final road level and formation level are only intended as an assistance to the contractor, and are not reliable for contruction unless other agreements are made in the specific project.


Motorway

ORD_MW_Machine-Control_Side_1.jpg


2-lane road​

ORD_2-LaneRoad_Machine-Control_Side_1.jpg



​​​